Romarco extends key contracts

Friday, Jun 15, 2012

TORONTO, June 14, 2012 /PRNewswire/ - ROMARCO MINERALS INC. (TSX: R) (the "Company") is pleased to announce that in light of the recently announced permit schedule, it has renegotiated a number of key contracts to re-align equipment deliveries for the development of the Haile Gold Mine.  These activities are part of an overall Company strategy for managing cash according to the new permit schedule.

Key Equipment

Romarco's Caterpillar ("CAT") mobile mine equipment for its Haile Gold Mine project in South Carolina is currently being held in inventory by the local CAT dealer, Blanchard Machinery Company ("BMC").  BMC will deliver the CAT equipment that was previously targeted for delivery by March 31, 2013 on a revised schedule aligned with the expected start of construction.  For BMC to maintain the inventory over the extended schedule, the Company will incur an additional $30,000/month, bringing the total monthly holding cost to approximately $230,000.  This agreement maintains the previously agreed pricing, ensures timely delivery of new equipment with tires, and allows the Company to defer the majority of the payment, approximately $29 million, until the earlier of September 30, 2013 or when the equipment is delivered to Haile.

Romarco has agreed with the local Hitachi shovel dealer, Flint Holdings ("FH") to align delivery with the expected start of construction. FH anticipates receiving the shovel in December 2012 and will maintain the shovel in its inventory until delivered to Haile.  At that time, the Company will pay FH a montly holding cost of approximately $11,000 and make monthly down payment installments of approximately $43,000.  This agreement maintains the previously agreed pricing, ensures timely delivery of the shovel, and allows the Company to defer the majority of the payment, approximately $2.5 million, until the equipment is delivered to Haile.

The manufacturer of the SAG and secondary Ball grinding mills has indicated it will re-align delivery and final payments by three to six months.  This will defer the approximate $5 million final payment over the first and second quarters of 2013.

The Company is advancing detail design engineering with a target to be 75 percent complete by the end of 2012.  Equipment specification and design that is critical for advancing engineering is being identified and manufacturers are being selected.  Romarco is purchasing the engineering necessary for continuing design. The equipment will be released for manufacture on a time line that coincides with project construction.  This process allows significant flexibility while minimizing cash expenditures and maintaining the project timeline.

About Romarco Minerals Inc.

Romarco Minerals Inc. is a gold development company focused on production primarily in the US.  The Company has completed a positive Feasibility study and is continuing exploration drilling and permitting for its flagship project, the Haile Gold Mine in South Carolina.

SOURCE ROMARCO MINERALS INC.

posted in:

Other Mining News

Rockwell announces positive pre-feasibility study for Wouterspan property 21-05-2013
Besra resumes operations at the Phuoc Son Mine in Vietnam after a temporary shutdown 21-05-2013
Fortuna discovers new high grade vein at Caylloma mine drilling intercepts 1.7 meters of 105 g/t Ag and 21 g/t Au 21-05-2013
Pöyry appointed to deliver EPCM services for concentrating plant expansion project at Kittilä gold mine 21-05-2013
Corvus Gold secures electrical power at the North Bullfrog project, Nevada, announces Director Departure 17-05-2013
TAD acquires the Iskut Copper Gold Prospect in BC 15-05-2013
Logistics management given prime attention by mining companies today 15-05-2013
Sustainable health and safety conditions a growing concern in the mining industry 15-05-2013
Western Graphite beginning Phase I program at Pure Flake Graphite Mine 14-05-2013
Potash Ridge accomplishes unconditional right to convert exploration lease into mining lease 14-05-2013

Advertisers