posted in:

Banro - www.youroilandgasnews.com

Banro announces the arrival of its refurbished gold plant at Twangiza and provides construction update

Tuesday, Jul 27, 2010

Banro Corporation
("Banro" or the "Company") (NYSE AMEX - "BAA"; TSX - "BAA") is pleased to
announce that the reconditioned gold processing plant, which the Company
acquired in Australia for re-assembly at its wholly-owned Twangiza gold
project in South Kivu Province of the Democratic Republic of the Congo (the
"DRC"), has begun arriving at the Twangiza site. The entire plant, which is
being transported by truck from Mombasa, Kenya in 140 - 40 foot containers,
including the break bulk items, is scheduled to arrive on site over the next
ten weeks.

The arrival on July 21, 2010 of the first fleet of trucks was greeted in
Bukavu, DRC, the capital of South Kivu province, with a public ceremony
hosted by the Governor and the Deputy Governor of South Kivu Province with
the participation of the chiefs of the chefferies overlapping the Twangiza
property and several other dignitaries. In his speech, the Governor of South
Kivu promised his Government's full support to Banro for the building of the
Twangiza gold mine.

The Company is also pleased to announce that construction of the Twangiza
mine is proceeding on schedule, with phase one earthworks having been
completed on June 28, 2010. Civil works at the plant site are well advanced,
with assembly of the reconditioned gold plant to begin in October this year.
The final civil work is scheduled for completion in June 2011. The Company
remains on schedule to complete construction of the Twangiza "Phase I" gold
mine in the fourth quarter of 2011.

Photographs highlighting construction progress at the Twangiza site can be
viewed on the Banro website at:
http://www.banro.com/s/TwangizaGoldPlantUpdate.asp?ReportID=380953.


Source: Canada Wire

posted in:

Other Mining News

Atlanta Gold Drilling Program confirms new Gold Bearing Zone at its Atlanta Property in Idho 03-09-2010
Luna Gold Defines 10 Exploration Targets at Aurizona Main 03-09-2010
Ascot Resources Commences Diamond Drilling on the Mt. Margaret Property 02-09-2010
Capstone Reports Results of Titan-24 Geophysical Survey at Minto Mine, Yukon 02-09-2010
Jaguar Mining Announces First Gold Pour at Caeté 01-09-2010
Gammon Gold Signs Definitive Agreement on the Los Jarros Properties, Chihuahua Mexico 01-09-2010
Dorato Receives Positive Results from Initial Metallurgical Testing 31-08-2010
Dianor Enters Into $10 Million Credit Agreement With Syndicate of Lenders 31-08-2010
Lake Shore Gold Expands Thunder Creek Rusk Zone, Announces Additional Wide, High-Grade Intercepts 30-08-2010
Black Hawk Exploration Announces Dun Glen Drilling Results and Gross Revenue Estimates for Monroe North Project of $580,000 30-08-2010

Advertisers